2020 SEWER IMPROVEMENTS

Overview

OVERVIEW

This project includes sewer line additions for the purpose of abandoning a sewer lift station near 1000 West Garden Dr.  The project will include Boring under the UTA railroad and State Street.

SCHEDULE

Project is scheduled for Summer of 2020 with a final completion date of Sept 30th.  Actual start date is TBD but is scheduled to last 60 days total.

(Updated 04/21/2020)

 

QUESTIONS

Please contact the Public Works Department 