top of page


700 South Sewer
Overview
OVERVIEW
The 700 South Sewer Project will replace the old sewer main in 700 South between approximately 1200 West and 910 West with a larger main to meet the needs of the city as it grows. Effective immediately the road will be closed with detours around the project in order to permit standard safety practices for construction. Access will be provided to local residents and businesses.
SCHEDULE
The project is scheduled to start June 15, 2020 and to be completed by August 15, 2020.
The sewer line will be replaced, then the road above the sewer line will be repaired.
(Updated 6/18/2020)
QUESTIONS
Please contact the Pleasant Grove
Public Works Department at 801-785-2941
with comments or questions related to this project.


bottom of page