2020 SEWER IMPROVEMENTS

Overview

OVERVIEW

This project includes sewer line additions for the purpose of abandoning a sewer lift station near 1000 West Garden Dr.  The project will include Boring under the UTA railroad and State Street.

SCHEDULE

Project is scheduled to start the week of Oct 12 and continue until complete.  Project completion may be extended till spring of 2021 depending on weather conditions.

(Updated 10/13/2020)

 

QUESTIONS

Please contact the Public Works Department 

at 801-785-2941 with comments or

questions related to this project.